Practice quiz · MRT1 · LIBF
Possible remedial works and actions lenders may take
Untimed topic quiz on what can be done about a defect and how a lender may respond: specialist remedial works and evidence, retentions, reinspections, undertakings, indemnity insurance, price changes, declining the security and explaining conditions to customers.
- Questions
- 12
- Time
- Untimed
- Pass mark
- 70%
- Format
- Knowledge check
Independent practice. Not an official LIBF exam. This sitting is part of a paid pack. Every qualification has a free paper you can sit without buying. Flag a question to jump back to it before you submit. All questions are on one page. Answering one scrolls you to the next; submit at the bottom. Optional tips are on each question if you want a nudge, they never name the answer.
Topics covered
- Possible remedial works and actions lenders may take
Sample questions with answers
The first 3 of the 12 questions in this quiz, with the answer and an explanation for each.
Question 1 · Possible remedial works and actions lenders may take
A lender agrees an advance of £178,500 on Callum Dyer’s purchase but holds back a £6,000 retention for roof repairs. How much of the advance is released at completion?
- A.£184,500, which is the advance plus the retention
- B.£178,500, which is the full advance as offered
- C.£172,500, which is the advance less the retention
- D.£6,000, which is the amount that is held back
Answer: C. £172,500, which is the advance less the retention
A retention is money the lender holds back from the advance until specified action is performed, as described in the UK Finance Mortgage Lenders’ Handbook. Only £172,500 is released at completion, and the £6,000 follows once the works are done to the lender’s satisfaction. Adding the retention, releasing the whole advance or releasing only the retention misreads how it works.
Question 2 · Possible remedial works and actions lenders may take
A lender is holding a retention for roof renewal on Rosa Marsh’s house. The roofer says the work is finished. What is normally needed before the lender releases the retention?
- A.A written request from Rosa confirming that she is satisfied with the work
- B.Evidence the works meet the condition, usually a valuer’s reinspection
- C.A period of six months with no leaks reported to the buildings insurer
- D.Renewal of the buildings insurance policy on the house for another year
Answer: B. Evidence the works meet the condition, usually a valuer’s reinspection
The lender is not obliged to release a retention unless the condition attached to it is fully satisfied. The usual check is a reinspection by the lender’s valuer, though some files accept documentary certificates. Rosa’s own satisfaction, a leak-free period or an insurance renewal do not show that the specified works meet the lender’s requirement.
Question 3 · Possible remedial works and actions lenders may take
A lender requires dry rot in the cellar joists of Kemal Ozdemir’s purchase to be treated before completion. Which evidence would the lender normally accept?
- A.A letter from the seller confirming that the rot has now been treated and fixed
- B.A treatment certificate from a specialist contractor the lender recognises
- C.Photographs taken by the buyer after the cellar has been cleaned and repainted
- D.A statement from the estate agent that the cellar is now dry and structurally sound
Answer: B. A treatment certificate from a specialist contractor the lender recognises
Dry rot needs the moisture source removed and the affected timber treated or replaced. Lenders commonly look for a specialist contractor, a method that matches the diagnosis and a treatment certificate their policy recognises. A seller’s letter, the buyer’s photographs and an estate agent’s opinion are not independent evidence that the work was done properly.
Keep going
- CeMAP 2 (MORT) mock exam pack · £15Every MRT1 paper and topic quiz in one pack.
- CeMAP online course · £179Written lessons in syllabus order, with every pack included.
- MRT1 (CeMAP 2) exam guideFormat, topics and every free and paid paper for the unit.
Other MRT1 papers
Independent practice written by Archway Learn. Not an LIBF exam paper, and not affiliated with or endorsed by LIBF.