How does the risk management process work?

Syllabus topic: Explain the risk management function and process.

In short

Dev and Anika Sharma run Brightwater Bakery in Leeds with 14 staff, two shops and a production unit. For years they dealt with risks as they appeared: an extinguisher here, a new policy there. When their broker, Ellis & Rowe, asked for a list of everything that could go wrong, they realised they had never ranked the risks.

Key facts

  • The process runs: identify, analyse and evaluate, control, finance, then monitor and review.
  • Analysis follows identification and comes before any control decision.
  • Risk appetite is the amount and type of risk the board will accept.
  • First line managers own risk, second line functions oversee it and internal audit gives independent assurance.
  • Avoidance stops the activity, reduction lowers frequency or severity, transfer moves the financial cost and retention funds it internally.
  • High-frequency, low-severity losses are retained and reduced; low-frequency, high-severity losses are transferred.
  • Expected loss is probability multiplied by severity, and a risk rating is likelihood multiplied by impact.
  • Net benefit of a control is the fall in expected loss minus the cost of the control.

Key terms

Risk appetite
The amount and type of risk a board or owner is willing to accept in pursuit of its objectives.
Risk register
The central record of identified risks with their owners, ratings, controls and actions.
Risk avoidance
Not undertaking the activity that creates the risk.
Risk reduction
Lowering the frequency or severity of losses while the activity continues.
Risk transfer
Passing the financial consequence of a loss to another party, for example by insurance or contract.
Risk retention
Accepting a loss and paying for it from the organisation’s own resources.
Internal audit
The third line of defence, giving the board independent assurance over risk management and controls.

Common exam trap

The trap: Once the risks are listed, the next step is to buy insurance or install controls.

Analysis comes next. Frequency and severity decide which risks matter and which treatment fits, and insurance is only one control option, not a stage of its own.

Monitoring comes last, because it judges controls that already exist.

Why it matters: Questions name a finished stage and ask what comes next.

Worked calculation: Expected loss of a production-unit fire

Ellis & Rowe estimates a 1 in 80 chance each year of a serious fire at the Brightwater production unit, which would cost £600,000 to rebuild.

  1. Step 1: Convert the chance to a percentage

    1 ÷ 80

    = 1.25%

    Express the odds as a probability.

  2. Step 2: Multiply by the severity

    1.25% × £600,000

    = £7,500 a year

    Expected loss is probability multiplied by severity.

Answer: The expected annual loss is £7,500.

This is the average yearly cost of bearing the risk, to compare with the price of insurance and controls.

3 practice questions

These come from the 12-question topic quiz. Pick an answer, then open the explanation.

  1. Question 1

    Which sequence correctly sets out the main stages of the risk management process?

    1. AIdentify, control, analyse, then monitor
    2. BAnalyse, identify, transfer, then review
    3. CControl, identify, analyse, then review
    4. DIdentify, analyse, control, then monitor
    Show the answer

    Answer: D

    Risk management starts by identifying the risks, then analysing and evaluating them for likelihood and impact, then deciding how to control them by avoidance, reduction, transfer or retention, and finally monitoring and reviewing the results. A risk cannot be controlled sensibly before it is analysed, and analysis needs the risk to have been identified first. Transfer is one control option, not a separate stage.

  2. Question 2

    A firm scores risks from 1 to 5 for likelihood and for impact and multiplies the two scores. What is the rating for a risk scored 4 for likelihood and 3 for impact?

    1. AA rating of 7
    2. BA rating of 4
    3. CA rating of 1
    4. DA rating of 12
    Show the answer

    Answer: D

    In a multiplicative risk matrix the rating is likelihood multiplied by impact, so 4 × 3 gives 12 out of a possible 25, usually placing the risk in an amber or red zone. Adding the scores gives 7, which is a different method. Taking the higher score gives 4, and the difference between the scores gives 1, neither of which combines likelihood and impact.

  3. Question 3

    Two years after fitting a new alarm system, a firm compares its theft claims with the period before installation. Which stage of risk management is it carrying out?

    1. AMonitoring and review
    2. BRisk identification
    3. CRisk analysis
    4. DRisk financing
    Show the answer

    Answer: A

    Monitoring and review checks whether controls are working and whether the risk profile has changed, feeding back into identification and analysis. Comparing claims before and after the alarm tests the effectiveness of a control already in place. Identification finds new risks, analysis measures likelihood and impact before a decision, and risk financing is about how retained or transferred losses are paid for.

Test yourself

A café has listed its hazards and scored each for likelihood and impact. Which stage comes next, and why?

Control comes next, because identification and analysis are complete. The scores now show which risks to avoid, reduce, transfer or retain.

A haulier subcontracts a hazardous cleaning task to a specialist firm that carries the liability. Which control method is this?

It is risk transfer. The activity and its financial consequences move to the contractor.

A risk has a 1 in 125 annual chance of a £250,000 loss. What is the expected annual loss?

1 ÷ 125 is 0.8%, and 0.8% × £250,000 is £2,000 a year.

Sources

Reviewed on 27 Oct 2026. Next review due 1 Jan 2027. Written by Archway Learn from the CII syllabus and the sources above.