Appraise the options for project management and site management responsibilities

Twelve applied questions on who runs a self-build site: self-management, main contractors, project managers and design-and-build, with CDM duties, budgets, retentions, VAT and lender requirements. Original Archway Learn practice, not past exam questions.

Questions
12
Time
Untimed
Pass mark
70%
Format
Knowledge check

Independent practice. Not an official LIBF exam. This sitting is part of a paid pack. Every qualification has a free paper you can sit without buying. Flag a question to jump back to it before you submit. All questions are on one page. Answering one scrolls you to the next; submit at the bottom. Optional tips are on each question if you want a nudge, they never name the answer.

Topics covered

  • Appraise the options for project management and site management responsibilities

Sample questions with answers

The first 3 of the 12 questions in this quiz, with the answer and an explanation for each.

  1. Question 1 · Appraise the options for project management and site management responsibilities

    Priya and Sam are building their own home and have hired four trades directly, without appointing a principal contractor. Under the Construction (Design and Management) Regulations 2015, who carries the client duties?

    1. A.Priya and Sam, because domestic clients keep the client duties when they hire trades directly
    2. B.The building control inspector, who visits the site at each statutory stage of the build
    3. C.The lender’s monitoring surveyor, because the lender releases funds against each stage
    4. D.The contractor in control of the construction phase of the project

    Answer: D. The contractor in control of the construction phase of the project

    Under CDM 2015 a domestic client’s duties pass to the contractor on a single-contractor job, or to the principal contractor where there is more than one. If no principal contractor is appointed, the contractor in control of the construction phase takes them on. The couple do not keep the duties, and neither building control nor the lender’s surveyor is a dutyholder for site safety.

  2. Question 2 · Appraise the options for project management and site management responsibilities

    Hannah has a fixed-price main contractor quote of £310,000. Managing the trades herself is estimated at £262,000, to which she adds a 15% contingency. If the contingency is fully spent, how much does self-managing save her?

    1. A.£48,000
    2. B.£8,700
    3. C.£40,800
    4. D.£1,500

    Answer: B. £8,700

    The contingency applies to the self-managed estimate: £262,000 × 1.15 = £301,300, which is £8,700 below the £310,000 fixed price. £48,000 ignores the contingency altogether; £40,800 wrongly applies 15% to the saving rather than the cost; £1,500 applies 15% to the fixed-price quote instead of the trades estimate. The narrow margin shows why self-management must be appraised against time and risk, not headline cost.

  3. Question 3 · Appraise the options for project management and site management responsibilities

    Leon has a fixed-price contract with a main contractor but agrees directly with the contractor’s electrician to add underfloor heating, paying her in cash. What is the main risk this creates?

    1. A.The whole contract turns into a cost-plus arrangement from that point onwards
    2. B.The extra work sits outside the fixed price and blurs who answers for it
    3. C.The contractor’s site insurance stops covering any part of the works in progress
    4. D.The lender must cancel the remaining stage payments and revalue the plot

    Answer: B. The extra work sits outside the fixed price and blurs who answers for it

    A fixed price protects the client only for the agreed scope. Variations should be instructed through the contractor so cost, programme and responsibility stay with one party. A side deal leaves the underfloor heating outside the contract, so defects or delays caused by it become a dispute. It does not convert the contract to cost-plus, end the contractor’s insurance or force the lender to cancel funding.