Differentiate the risks for lender and borrower
Untimed topic quiz on how the risks of a self-build project fall differently on the lender and the borrower: security value, cost overruns, delays, interest rates, contractor failure, abandonment, insurance, warranties and valuation changes, with worked figures (original Archway Learn practice, not a real exam).
- Questions
- 12
- Time
- Untimed
- Pass mark
- 70%
- Format
- Knowledge check
Independent practice. Not an official LIBF exam. This sitting is part of a paid pack. Every qualification has a free paper you can sit without buying. Flag a question to jump back to it before you submit. All questions are on one page. Answering one scrolls you to the next; submit at the bottom. Optional tips are on each question if you want a nudge, they never name the answer.
Topics covered
- Differentiate the risks for lender and borrower
Sample questions with answers
The first 3 of the 12 questions in this quiz, with the answer and an explanation for each.
Question 1 · Differentiate the risks for lender and borrower
Why is a lender on a self-build project usually more exposed than on the purchase of a finished house?
- A.The lender cannot take a charge over the plot until the building control completion certificate is issued
- B.MCOB requires the lender to meet any cost overrun above the original budget in full
- C.If the project stalls, the unfinished building may be worth less than the money already advanced
- D.The borrower is not allowed to pay interest on the loan until the final stage is released
Answer: C. If the project stalls, the unfinished building may be worth less than the money already advanced
During a build the lender’s security is a plot and a partly built structure, whose value may not match the funds already released. If the project stalls, a forced sale of an unfinished building can leave a shortfall. The lender takes its charge over the land at the outset, MCOB does not make lenders pay for overruns, and interest is normally charged on amounts drawn.
Question 2 · Differentiate the risks for lender and borrower
Priya’s self-build costs £350,000 (£100,000 for the plot and £250,000 to build) with a fixed loan of £280,000. The build then overruns by £40,000 and the facility cannot be increased. How much must Priya fund from her own money?
- A.£70,000
- B.£150,000
- C.£110,000
- D.£78,000
Answer: C. £110,000
The total cost becomes £390,000. With the loan fixed at £280,000, Priya must find £390,000 − £280,000 = £110,000, which is £40,000 more than the £70,000 originally planned. £70,000 ignores the overrun, £150,000 counts the overrun twice, and £78,000 wrongly assumes the lender will keep funding 80% of the higher cost.
Question 3 · Differentiate the risks for lender and borrower
A self-build lender releases funds in arrears after each inspection. Which risk does this arrangement reduce for the lender if the builder later fails?
- A.The risk that the borrower cannot afford the monthly interest
- B.The risk of paying for work that has not yet been carried out
- C.The risk that the borrower chooses a variable rather than a fixed rate
- D.The risk that planning permission will expire before the work starts
Answer: B. The risk of paying for work that has not yet been carried out
Paying in arrears means each release matches work a surveyor has seen, so if a builder becomes insolvent the lender has not paid for stages that were never built. Advance payments leave the lender exposed to funds spent without matching value. Arrears releases do not affect interest affordability, the choice of rate type or planning expiry, which are separate risks.
Keep going
- CeMAP Diploma AMA pack · £25Every AMA paper and topic quiz in one pack.
- CeMAP Diploma online course · £249Written lessons in syllabus order, with every pack included.
- AMA (CeMAP Diploma) exam guideFormat, topics and every free and paid paper for the unit.
Other AMA papers
Independent practice written by Archway Learn. Not an LIBF exam paper, and not affiliated with or endorsed by LIBF.