Discuss the implications of buying ‘off plan’
Untimed practice quiz on buying off plan: down-valuations, offer expiry, exchange risk, warranties, incentives, deposit protection and SDLT timing (original Archway Learn practice, not a real exam).
- Questions
- 12
- Time
- Untimed
- Pass mark
- 70%
- Format
- Knowledge check
Independent practice. Not an official LIBF exam. This sitting is part of a paid pack. Every qualification has a free paper you can sit without buying. Flag a question to jump back to it before you submit. All questions are on one page. Answering one scrolls you to the next; submit at the bottom. Optional tips are on each question if you want a nudge, they never name the answer.
Topics covered
- Discuss the implications of buying ‘off plan’
Sample questions with answers
The first 3 of the 12 questions in this quiz, with the answer and an explanation for each.
Question 1 · Discuss the implications of buying ‘off plan’
Aisha exchanged contracts on an off-plan flat at £320,000 with a mortgage offer at 90% loan-to-value. At completion the lender’s revaluation comes in at £300,000. If the lender lends 90% of the lower figure, how much extra must Aisha find?
- A.£20,000
- B.£18,000
- C.£2,000
- D.£50,000
Answer: B. £18,000
The price stays at £320,000 because contracts have been exchanged. Her original loan was 90% of £320,000, or £288,000; the new loan is 90% of £300,000, or £270,000. The loan falls by £18,000, which she must find on top of her £32,000 deposit. £20,000 is the fall in value rather than in the loan, £2,000 is the deposit share of that fall, and £50,000 is her total cash need.
Question 2 · Discuss the implications of buying ‘off plan’
Ben exchanged contracts on an off-plan house 14 months ago, paying a 10% deposit of £34,000. His mortgage offer has expired and his new lender will lend less. If he cannot complete, what is the likely consequence?
- A.He can withdraw and recover his deposit, because his original mortgage offer has expired
- B.He can delay completion until a new offer is issued, as the developer must wait for it
- C.He risks losing his deposit and being sued by the developer for any further loss
- D.He can assign the contract back to the developer at no cost under consumer protection law
Answer: C. He risks losing his deposit and being sued by the developer for any further loss
Exchange creates a binding contract. If the buyer fails to complete after a notice to complete, the seller can usually keep the 10% deposit, resell and claim further losses such as a lower resale price. Expiry of a mortgage offer is the buyer’s risk, not a ground for withdrawal, and a developer need not wait indefinitely or take the contract back. Off-plan buyers should therefore check offer validity against the expected build date.
Question 3 · Discuss the implications of buying ‘off plan’
Kofi reserves an off-plan apartment due to complete in about 15 months. His broker finds a lender whose mortgage offers are valid for 6 months. What is the main planning issue?
- A.The offer may lapse before completion, so an extension or new application may be needed
- B.The offer cannot be issued until the building is finished and has been fully valued by the lender
- C.The offer locks in today’s valuation and interest rate for the whole build period regardless
- D.The lender cannot make an offer on a property where the buyer has paid a reservation fee
Answer: A. The offer may lapse before completion, so an extension or new application may be needed
Off-plan completions can be a year or more after exchange, while many mortgage offers last around six months, with some lenders allowing longer validity or extensions on new build. If the offer lapses, the buyer must reapply at the rates, criteria and valuation then current. A lender can issue an offer before completion, the valuation is not fixed for the whole build, and a reservation fee does not prevent lending.
Keep going
- CeMAP Diploma AMA pack · £25Every AMA paper and topic quiz in one pack.
- CeMAP Diploma online course · £249Written lessons in syllabus order, with every pack included.
- AMA (CeMAP Diploma) exam guideFormat, topics and every free and paid paper for the unit.
Other AMA papers
Independent practice written by Archway Learn. Not an LIBF exam paper, and not affiliated with or endorsed by LIBF.