Practice quiz · AMA · LIBF

Discuss the market for self-build projects

Untimed practice quiz on self-build finance: stage payments, land advances, planning, warranties, VAT refunds, the infrastructure levy, site insurance and regulation (original Archway Learn practice, not a real exam).

Questions
12
Time
Untimed
Pass mark
70%
Format
Knowledge check

Independent practice. Not an official LIBF exam. This sitting is part of a paid pack. Every qualification has a free paper you can sit without buying. Flag a question to jump back to it before you submit. All questions are on one page. Answering one scrolls you to the next; submit at the bottom. Optional tips are on each question if you want a nudge, they never name the answer.

Topics covered

  • Discuss the market for self-build projects

Sample questions with answers

The first 3 of the 12 questions in this quiz, with the answer and an explanation for each.

  1. Question 1 · Discuss the market for self-build projects

    Tobias is building his own home but has limited savings. His self-build mortgage releases funds in arrears. What does this mean for him?

    1. A.He receives each stage payment before work on that stage starts, so savings are not needed
    2. B.He must pay for each stage first and is reimbursed after the lender’s valuer inspects it
    3. C.He receives the whole loan at the start, with interest charged on the full amount
    4. D.He receives the whole loan once the house is finished and signed off by building control

    Answer: B. He must pay for each stage first and is reimbursed after the lender’s valuer inspects it

    With arrears stage payments the lender releases money after each stage has been completed and inspected, so the self-builder needs cash or other funding to pay for the work first. Advance stage payment products release money before each stage to ease cash flow. Self-build loans are not released in one sum at the start or the end, and interest is charged on the amount drawn so far.

  2. Question 2 · Discuss the market for self-build projects

    Ines is buying a building plot for £150,000 with full planning permission. Her self-build lender will advance up to 75% of the land cost at purchase. How much deposit does she need for the plot?

    1. A.£112,500
    2. B.£37,500
    3. C.£15,000
    4. D.£22,500

    Answer: B. £37,500

    A 75% advance on the £150,000 land cost is £112,500, leaving a 25% deposit of £37,500 from Ines. Self-build lenders usually lend a lower share against bare land than against a finished house, because a plot is harder to sell if the project fails. £112,500 is the advance rather than the deposit, and £15,000 and £22,500 assume 90% and 85% advances, which self-build lenders rarely offer against land.

  3. Question 3 · Discuss the market for self-build projects

    Rowan completed his self-built home in March 2026. He paid £72,000, including VAT at 20%, for building materials. Under HMRC’s DIY housebuilders scheme, how much VAT can he reclaim, and by when must he claim?

    1. A.£12,000, with the claim made within 6 months of completion
    2. B.£14,400, with the claim made within 6 months of completion
    3. C.£12,000, with the claim made within 3 months of completion
    4. D.£14,400, with the claim made within 12 months of completion

    Answer: A. £12,000, with the claim made within 6 months of completion

    VAT included in a price at 20% is one sixth of that price, so £72,000 contains £12,000 of VAT; taking 20% of the gross figure overstates it at £14,400. For claims made on or after 5 December 2023, a single claim must be made within 6 months of completion, while the 3-month limit applied to earlier claims. Builders’ services on a new dwelling are normally zero-rated, so most claims concern materials.

Keep going