Explain lenders’ requirements

Twelve applied questions on what lenders require for self-build mortgages: planning, borrower contribution, stage releases, inspections, contingency, insurance, warranties and occupation (original Archway Learn practice, not a real exam).

Questions
12
Time
Untimed
Pass mark
70%
Format
Knowledge check

Independent practice. Not an official LIBF exam. This sitting is part of a paid pack. Every qualification has a free paper you can sit without buying. Flag a question to jump back to it before you submit. All questions are on one page. Answering one scrolls you to the next; submit at the bottom. Optional tips are on each question if you want a nudge, they never name the answer.

Topics covered

  • Explain lenders’ requirements

Sample questions with answers

The first 3 of the 12 questions in this quiz, with the answer and an explanation for each.

  1. Question 1 · Explain lenders’ requirements

    Rosa has bought a plot with outline planning permission for a single house. What will her self-build lender require before it releases money for the build itself?

    1. A.Detailed planning consent and building regulations approval
    2. B.Outline permission alone, as it confirms a house may be built there
    3. C.A building control completion certificate for the finished home
    4. D.A structural warranty certificate issued by the local planning authority

    Answer: A. Detailed planning consent and building regulations approval

    Outline permission accepts the principle of development but leaves details to be approved, so building cannot start on it alone. Lenders want full or reserved matters approval and building regulations approval before funding works. A completion certificate is issued only when the house is finished, and structural warranties come from warranty providers or professional consultants, not the planning authority.

  2. Question 2 · Explain lenders’ requirements

    Rosa’s plot cost £120,000 and her fixed-price build contract is £280,000. Her lender advances 75% of the plot cost and 75% of each build stage. Ignoring contingency, how much of her own money does she need?

    1. A.£30,000
    2. B.£70,000
    3. C.£100,000
    4. D.£120,000

    Answer: C. £100,000

    The total project cost is £400,000 and the lender funds 75%, or £300,000, so Rosa must provide 25%, or £100,000, across the plot and the stages. £30,000 is her share of the plot only, £70,000 her share of the build only, and £120,000 assumes she must buy the plot outright. Lenders expect borrower equity because unfinished sites are weak security.

  3. Question 3 · Explain lenders’ requirements

    Sam has little cash and is worried he cannot pay his builder for each stage before the lender releases the funds. Which product feature addresses this?

    1. A.Arrears stage payments, released after each stage is inspected
    2. B.Advance stage payments, released at the start of each stage
    3. C.A single advance of the whole build cost when the plot is bought
    4. D.An interest-only further advance arranged once the house is finished

    Answer: B. Advance stage payments, released at the start of each stage

    Most self-build mortgages pay in arrears, so the borrower funds a stage and is reimbursed after inspection. Advance stage payment products release money before each stage begins, easing cash flow for borrowers like Sam. Arrears payments cause his problem rather than solve it, no lender advances the whole build cost on plot purchase, and a post-completion advance does not pay for the build as it happens.