Who should manage a self-build project and site?
Syllabus topic: Appraise the options for project management and site management responsibilities
In short
Elaine and Kenny Ferguson in Glasgow want to borrow £30,000 more to extend their home. Kenny, a joiner, thinks he can run the job himself and save the contractor’s margin, but Elaine works shifts and worries about who answers if the plumbing fails. Their adviser Megan Rowe must weigh savings against time, skill, safety duties and the lender’s need for evidence.
Key facts
- Self-management suits skilled owners with time and a simple design; others need a contractor or a project manager.
- Domestic client duties under CDM 2015 pass to the contractor or principal contractor, never to building control or the lender’s surveyor.
- Notify the HSE if the work lasts over 30 working days with more than 20 workers at once, or exceeds 500 person-days.
- Apply contingency to the self-managed estimate, not to the saving: £298,000 plus 12% is £333,760.
- Compare a project manager’s fee with the delay costs avoided: £25,200 less £9,000 is £16,200.
- Retention is a percentage of the contract sum, released half at completion and half after the defects period.
- Variations go through the main contractor; side deals fall outside the fixed price.
- The DIY housebuilders scheme allows one VAT claim within 6 months of completion; extensions do not qualify.
Key terms
- Principal contractor
- The contractor who plans, manages and coordinates the construction phase where there is more than one contractor.
- Retention
- A percentage of the contract sum held back until completion and the end of the defects period.
- Professional Consultant’s Certificate
- A certificate from an insured consultant who monitored the build, accepted by lenders in place of a warranty and valid for 6 years.
- DIY housebuilders scheme
- HMRC’s scheme for reclaiming VAT on materials for a new home, claimed within 6 months of completion.
Common exam trap
The trap: A couple who hire their own trades directly keep the client duties, or the lender’s monitoring surveyor takes them on.
Domestic client duties pass to the contractor or principal contractor. With several trades and no principal contractor appointed, the contractor in control of the construction phase carries them.
Why it matters: Confusion over who holds the duties leaves site safety unowned.
Worked calculation: Is the project notifiable?
Bethan’s self-build will take 75 working days, with 9 workers on site every day.
Step 1: Test the first limb
= Not met
The job lasts more than 30 working days, but 9 workers is below the 20-worker threshold.
Step 2: Count person-days
9 workers × 75 days
= 675
One person-day is one worker for one shift.
Step 3: Test the second limb
= Met
675 is more than 500, so the project is notifiable.
Answer: The project must be notified to the HSE.
The person-days limb catches long jobs with small teams.
3 practice questions
These come from the 12-question topic quiz. Pick an answer, then open the explanation.
Question 1
Priya and Sam are building their own home and have hired four trades directly, without appointing a principal contractor. Under the Construction (Design and Management) Regulations 2015, who carries the client duties?
- APriya and Sam, because domestic clients keep the client duties when they hire trades directly
- BThe building control inspector, who visits the site at each statutory stage of the build
- CThe lender’s monitoring surveyor, because the lender releases funds against each stage
- DThe contractor in control of the construction phase of the project
Show the answer
Answer: D
Under CDM 2015 a domestic client’s duties pass to the contractor on a single-contractor job, or to the principal contractor where there is more than one. If no principal contractor is appointed, the contractor in control of the construction phase takes them on. The couple do not keep the duties, and neither building control nor the lender’s surveyor is a dutyholder for site safety.
Question 2
Kofi wants one firm to answer for both the design and the construction of his new home. Under a design-and-build contract, where does responsibility for design defects usually sit?
- AWith his own architect, while the contractor answers for workmanship alone
- BWith the local authority, once building regulations approval has been granted
- CWith the warranty provider, once it has registered the plot for structural cover
- DWith the contractor, which takes on design as well as construction risk
Show the answer
Answer: D
In design-and-build procurement the contractor is responsible for design and construction, giving the client a single point of responsibility. Under a traditional architect-led route the client’s architect answers for design and the contractor for workmanship, which is the split Kofi wants to avoid. Building regulations approval does not transfer design liability, and a warranty provider insures specified defects rather than taking on design responsibility.
Question 3
Sofia works long hours and has no building experience. She wants one party to coordinate the trades, the programme and site safety for her new home. Which route best matches her objective?
- ASelf-managing the build, with a weekly site visit from her architect
- BA main contractor on a fixed-price contract, acting as principal contractor
- CHiring each trade directly under a separate contract for each package
- DBuying a timber-frame kit and organising her own labour for the rest of the build
Show the answer
Answer: B
A main contractor appointed as principal contractor coordinates the trades, runs the programme and takes on the client’s CDM duties, while a fixed price limits Sofia’s cost risk. Weekly architect visits do not move day-to-day coordination off her. Hiring trades directly or organising her own labour around a kit leaves her coordinating several contractors, which her time and experience cannot support.
Test yourself
A £500,000 build has a project manager at 6% of cost. Without one, the owner expects a 3-month overrun costing £2,000 a month in total. What is the net cost of hiring?
The fee is £30,000 and the overrun avoided is £6,000, so the net cost is £24,000.
A project lasts 40 working days with at most 12 workers. Does it need notifying to the HSE?
Only if it exceeds 500 person-days. At 12 workers for 40 days the total is at most 480, so it is not notifiable.
Why might a client choose design and build over a traditional architect-led contract?
The contractor answers for both design and construction, giving one point of responsibility. In the traditional route the architect answers for design and the contractor for workmanship.
Sources
- CeMAP syllabus, LIBF / Walbrook Institute London (March 2026)
- CDM 2015: domestic clients, Health and Safety Executive
- Construction (Design and Management) Regulations 2015, regulation 6, legislation.gov.uk
- Claim a VAT refund if you’re a DIY housebuilder, GOV.UK / HMRC
- UK Finance Mortgage Lenders’ Handbook: Professional Consultant’s Certificate, UK Finance
Reviewed on 28 Oct 2026. Next review due 6 Apr 2027. Written by Archway Learn from the LIBF syllabus and the sources above.